LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0063 · Wind · Hardeman County

Supra Wind

Supra Wind is a 206 MW wind project in Hardeman County, Texas, connecting at Tap #6101 Riley 7A to #60505 Edithcla 7B 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/23/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0063
Capacity
206 MW
Fuel
Wind (WT)
Interconnecting entity
NextEra Energy Interconnection Holdings, LLC
Projected COD
12/23/2027
Entered queue
06/29/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/29/2023
    Entered the queue with 206 MW, projected COD 12/23/2027
  • 06/29/2023
    Screening → FIS Requested