ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0056 · Wind · Pecos County

Laurel Wind Energy Center

Laurel Wind Energy Center is a 307 MW wind project in Pecos County, Texas, connecting at Tap Solstice to Bakersfield (Bus# 60404 -76002) 345kV Ckt 2 and. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0056
Capacity
307 MW
Fuel
Wind (WT)
Interconnecting entity
LAUREL ENERGY CENTER, LLC
Projected COD
12/31/2027
Entered queue
06/08/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/25/2024
    FIS Requested → IA Signed
  • 06/08/2023
    Entered the queue with 307 MW, projected COD 12/31/2027
  • 06/08/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.