LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0734 · BESS · Pecos County

Alamo Street BESS2

Alamo Street BESS2 is a 10 MW battery storage project in Pecos County, Texas, connecting at Alamo Street Sub TNP. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/30/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0734
Capacity
10 MW
Fuel
BESS (BA)
Interconnecting entity
Momentum Pilsner, LLC
Projected COD
03/30/2027
Entered queue
02/01/2023
ERCOT zone
WEST
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/01/2023
    Entered the queue with 10 MW, projected COD 03/30/2027
  • 02/01/2023
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.