26INR0685 · Gas · Reeves County
Exergy Energy West Texas Natural Gas Reciprocating Power I
Exergy Energy West Texas Natural Gas Reciprocating Power I is a 400 MW natural gas project in Reeves County, Texas, connecting at 38095 TNJACKRBT1 138kV. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 05/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0685
- Capacity
- 400 MW
- Fuel
- Gas (IC)
- Substation
- 38095 TNJACKRBT1 138kV
- County
- Reeves County
- Interconnecting entity
- August Partners LLC
- Projected COD
- 05/01/2027
- Entered queue
- 07/22/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/22/2025Entered the queue with 400 MW, projected COD 05/01/2027
Other projects at this substation