LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0654 · BESS · Atascosa County

Great Hambino BESS

COD delayed 1×

Great Hambino BESS is a 123 MW battery storage project in Atascosa County, Texas, connecting at #5700 Miracle Lake Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0654
Capacity
123 MW
Fuel
BESS (BA)
Interconnecting entity
Atascosa BESS, LLC
Projected COD
10/01/2028
Entered queue
09/10/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/01/2027 → 10/01/2028 (+12 months)
  • 09/10/2025
    Entered the queue with 123 MW, projected COD 10/01/2027
  • 09/10/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.