26INR0612 · BESS · Clay County

Clay County Yang Storage

Clay County Yang Storage is a 308 MW battery storage project in Clay County, Texas, connecting at 1458 Cobb Switching Station 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/16/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0612
Capacity
308 MW
Fuel
BESS (BA)
Interconnecting entity
DM-CCY, LLC
Projected COD
04/16/2029
Entered queue
12/20/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Capacity 307 → 308 MW
  • 12/20/2024
    Entered the queue with 307 MW, projected COD 04/16/2029
  • 12/20/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.