26INR0612 · BESS · Clay County
Clay County Yang Storage
Clay County Yang Storage is a 308 MW battery storage project in Clay County, Texas, connecting at 1458 Cobb Switching Station 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/16/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0612
- Capacity
- 308 MW
- Fuel
- BESS (BA)
- Substation
- 1458 Cobb Switching Station 345 kV
- County
- Clay County
- Interconnecting entity
- DM-CCY, LLC
- Projected COD
- 04/16/2029
- Entered queue
- 12/20/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Capacity 307 → 308 MW
- 12/20/2024Entered the queue with 307 MW, projected COD 04/16/2029
- 12/20/2024Screening → FIS Requested