26INR0411 · BESS · Madison County
Tex-Bar ESS
Tex-Bar ESS is a 202 MW battery storage project in Madison County, Texas, connecting at Tap 345kV JEWETT_S5 (#3390) -- SINGLETON (#44645). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/08/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0411
- Capacity
- 202 MW
- Fuel
- BESS (BA)
- County
- Madison County
- Interconnecting entity
- Tex-Bar ESS LLC
- Projected COD
- 09/08/2029
- Entered queue
- 02/26/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/26/2025FIS Approved → IA Signed
- 09/26/2024FIS Requested → FIS Approved
- 02/26/2024Entered the queue with 202 MW, projected COD 09/08/2029
- 02/26/2024Screening → FIS Requested