Madison County power projects
Madison County, Texas has 4 active power projects totalling 814 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 613 MW (75%). The largest single project is Masava Storage (257 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
0.8 GW capacity
IA signed or later
2
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Madison County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Masava Storage | BESS | 257 | tap 345 kV 46020 Limestone Plant - 967 Gibbons Creek ckt 18 | FIS Requested | 09/30/2028 |
| Tex-Bar ESS | BESS | 202 | Tap 345kV JEWETT_S5 (#3390) -- SINGLETON (#44645) | IA Signed | 09/08/2029 |
| Savannah Oaks Solar | Solar | 201 | Tap 345kV 46020 Limestone Plant - 967 Gibbons Creek | FIS Requested | 09/30/2028 |
| SOSA Storage | BESS | 155 | Tap 138kV 25 North Zulch - 47 Hilltop Lakes | IA Signed | 07/20/2027 |
For residents and landowners
- What power projects are planned in Madison County?
- ERCOT's October 2026 report lists 4 active projects in Madison County totalling 814 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.