Nanulak BESS is a 182 MW battery storage project in Reeves County, Texas, connecting at 38113 TNCOYOTSPG1 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0385
Capacity
182 MW
Fuel
BESS (BA)
Interconnecting entity
Nanulak BESS, L.L.C.
Projected COD
06/30/2027
Entered queue
03/22/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 03/15/2027 → 06/30/2027 (+4 months)
  • 06/06/2026
    FIS Requested → FIS Approved
  • 11/19/2025
    FIS Approved → IA Signed
  • 03/06/2025
    Screening → FIS Requested
  • 03/22/2024
    Entered the queue with 182 MW, projected COD 03/15/2027