26INR0385 · BESS · Reeves County
Nanulak BESS
COD delayed 1×
Nanulak BESS is a 182 MW battery storage project in Reeves County, Texas, connecting at 38113 TNCOYOTSPG1 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0385
- Capacity
- 182 MW
- Fuel
- BESS (BA)
- Substation
- 38113 TNCOYOTSPG1 138kV
- County
- Reeves County
- Interconnecting entity
- Nanulak BESS, L.L.C.
- Projected COD
- 06/30/2027
- Entered queue
- 03/22/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 03/15/2027 → 06/30/2027 (+4 months)
- 06/06/2026FIS Requested → FIS Approved
- 11/19/2025FIS Approved → IA Signed
- 03/06/2025Screening → FIS Requested
- 03/22/2024Entered the queue with 182 MW, projected COD 03/15/2027