LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0316 · BESS · Throckmorton County

Lonesome Dove BESS

Withdrawn

Lonesome Dove BESS is a 256 MW battery storage project in Throckmorton County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0316
Capacity
256 MW
Fuel
BESS
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
09/11/2024
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/11/2024
    Listed as inactive

Other projects at this substation

No other projects at this substation.