LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0218 · BESS · Coke County

Fort Chadbourne Cattle BESS

Fort Chadbourne Cattle BESS is a 50 MW battery storage project in Coke County, Texas, connecting at 6324 Fort Chadbourne 138 kv. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/29/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0218
Capacity
50 MW
Fuel
BESS (BA)
Interconnecting entity
Fort Chadbourne BESS
Projected COD
06/29/2027
Entered queue
07/31/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/31/2023
    Entered the queue with 50 MW, projected COD 06/29/2027
  • 07/31/2023
    Screening → FIS Requested