26INR0028 · Solar · Victoria County
HyFuels Calhoun Solar
HyFuels Calhoun Solar is a 302 MW solar project in Victoria County, Texas, connecting at Tap 345kV 8715 RADIANT7A - 8728 COBRA7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/07/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0028
- Capacity
- 302 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 8715 RADIANT7A - 8728 COBRA7A
- County
- Victoria County
- Interconnecting entity
- HyFuels Green Lake Solar LLC
- Projected COD
- 10/07/2028
- Entered queue
- 10/18/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/07/2023Screening → FIS Requested
- 10/18/2022Entered the queue with 302 MW, projected COD 10/07/2028
Other projects at this substation
No other projects at this substation.