26INR0028 · Solar · Victoria County

HyFuels Calhoun Solar

HyFuels Calhoun Solar is a 302 MW solar project in Victoria County, Texas, connecting at Tap 345kV 8715 RADIANT7A - 8728 COBRA7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/07/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0028
Capacity
302 MW
Fuel
Solar (PV)
Interconnecting entity
HyFuels Green Lake Solar LLC
Projected COD
10/07/2028
Entered queue
10/18/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/07/2023
    Screening → FIS Requested
  • 10/18/2022
    Entered the queue with 302 MW, projected COD 10/07/2028

Other projects at this substation

No other projects at this substation.