26INR0021 · Wind · Victoria County
Crossroads Wind
COD delayed 1×
Crossroads Wind is a 277 MW wind project in Victoria County, Texas, connecting at 80090 Dokmai 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0021
- Capacity
- 277 MW
- Fuel
- Wind (WT)
- Substation
- 80090 Dokmai 138 KV
- County
- Victoria County
- Interconnecting entity
- HyFuels Green Lake Wind LLC
- Projected COD
- 02/28/2028
- Entered queue
- 09/27/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/30/2027 → 02/28/2028 (+5 months)
- 10/01/2026Capacity 277 → 277 MW
- 05/28/2026FIS Requested → FIS Approved
- 07/24/2024FIS Approved → IA Signed
- 06/16/2023Screening → FIS Requested
- 09/27/2022Entered the queue with 277 MW, projected COD 09/30/2027
Other projects at this substation
No other projects at this substation.