LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0021 · Wind · Victoria County

Crossroads Wind

COD delayed 1×

Crossroads Wind is a 277 MW wind project in Victoria County, Texas, connecting at 80090 Dokmai 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0021
Capacity
277 MW
Fuel
Wind (WT)
Interconnecting entity
HyFuels Green Lake Wind LLC
Projected COD
02/28/2028
Entered queue
09/27/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/30/2027 → 02/28/2028 (+5 months)
  • 10/01/2026
    Capacity 277 → 277 MW
  • 05/28/2026
    FIS Requested → FIS Approved
  • 07/24/2024
    FIS Approved → IA Signed
  • 06/16/2023
    Screening → FIS Requested
  • 09/27/2022
    Entered the queue with 277 MW, projected COD 09/30/2027

Other projects at this substation

No other projects at this substation.