25INR0610 · BESS · Medina County

Adam Bryant BESS

Adam Bryant BESS is a 100 MW battery storage project in Medina County, Texas, connecting at Tap 138kV 5225 HONDO – 5819 HONDO CREEK. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0610
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
Adam Bryant BESS LLC
Projected COD
12/01/2027
Entered queue
02/26/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/12/2024
    Screening → FIS Requested
  • 02/26/2024
    Entered the queue with 100 MW, projected COD 12/01/2027

Other projects at this substation

No other projects at this substation.