25INR0558 · BESS · Throckmorton County
Ayass BESS
Ayass BESS is a 51 MW battery storage project in Throckmorton County, Texas, connecting at 6206 Bush Knob 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0558
- Capacity
- 51 MW
- Fuel
- BESS (BA)
- Substation
- 6206 Bush Knob 69kV
- County
- Throckmorton County
- Interconnecting entity
- Harvick BESS, LLC
- Projected COD
- 12/30/2028
- Entered queue
- 11/15/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/15/2023Entered the queue with 51 MW, projected COD 12/30/2028
- 11/15/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.