LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0558 · BESS · Throckmorton County

Ayass BESS

Ayass BESS is a 51 MW battery storage project in Throckmorton County, Texas, connecting at 6206 Bush Knob 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0558
Capacity
51 MW
Fuel
BESS (BA)
Interconnecting entity
Harvick BESS, LLC
Projected COD
12/30/2028
Entered queue
11/15/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/15/2023
    Entered the queue with 51 MW, projected COD 12/30/2028
  • 11/15/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.