25INR0248 · BESS · Wilson County
Strawberry Acres Storage
Strawberry Acres Storage is a 157 MW battery storage project in Wilson County, Texas, connecting at 5132 Eagle Creek Substation 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0248
- Capacity
- 157 MW
- Fuel
- BESS (BA)
- Substation
- 5132 Eagle Creek Substation 138kV
- County
- Wilson County
- Interconnecting entity
- Strawberry Acres Energy Center, LLC
- Projected COD
- 09/30/2028
- Entered queue
- 11/15/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/27/2025FIS Requested → FIS Approved
- 11/15/2022Entered the queue with 157 MW, projected COD 09/30/2028
- 11/15/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.