ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0195 · Solar · Uvalde County

Photo Solar 2

Withdrawn

Photo Solar 2 is a 300 MW solar project in Uvalde County, Texas, connecting at 5885 Downie 138kV. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0195
Capacity
300 MW
Fuel
Solar (PV)
Interconnecting entity
CED Development Inc.
Projected COD
05/31/2028
Entered queue
09/15/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/14/2026
    Listed as cancelled
  • 09/15/2022
    Entered the queue with 300 MW, projected COD 05/31/2028
  • 09/15/2022
    Screening → FIS Requested

Other projects at this substation

SUNSETTER BESSBESS100 MWWithdrawn
PHOTO BESS 1BESS75 MWWithdrawn
PHOTO BESS 2BESS150 MWWithdrawn
Photo Solar 1Solar150 MWWithdrawn