24INR0121 · BESS · Uvalde County
PHOTO BESS 1
Withdrawn
PHOTO BESS 1 is a 75 MW battery storage project in Uvalde County, Texas, connecting at 5885 Downie 138kV. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0121
- Capacity
- 75 MW
- Fuel
- BESS (BA)
- Substation
- 5885 Downie 138kV
- County
- Uvalde County
- Interconnecting entity
- CED Development Inc.
- Projected COD
- 09/01/2027
- Entered queue
- 10/29/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/14/2026Listed as cancelled
- 05/13/2022Screening → FIS Requested
- 10/29/2021Entered the queue with 75 MW, projected COD 09/01/2027
Other projects at this substation
| SUNSETTER BESS | BESS | 100 MW | Withdrawn |
| PHOTO BESS 2 | BESS | 150 MW | Withdrawn |
| Photo Solar 1 | Solar | 150 MW | Withdrawn |
| Photo Solar 2 | Solar | 300 MW | Withdrawn |