LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0049 · Solar · Upton County

Point Mountain Solar

Withdrawn

Point Mountain Solar is a 514 MW solar project in Upton County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0049
Capacity
514 MW
Fuel
Solar
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
10/07/2024
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/07/2024
    Listed as inactive

Other projects at this substation

No other projects at this substation.