24INR0452 · Solar · Pecos County
Longfellow Solar I
Longfellow Solar I is a 178 MW solar project in Pecos County, Texas, connecting at 38431 TNCENTRY1_1 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0452
- Capacity
- 178 MW
- Fuel
- Solar (PV)
- Substation
- 38431 TNCENTRY1_1 138 KV
- County
- Pecos County
- Interconnecting entity
- CENTURY GAS PROCESSING, LLC
- Projected COD
- 12/31/2028
- Entered queue
- 11/07/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/15/2025FIS Requested → IA Signed
- 04/17/2023Screening → FIS Requested
- 11/07/2022Entered the queue with 178 MW, projected COD 12/31/2028
Other projects at this substation
| Rock House Draw Gas | Gas | 523 MW | FIS Requested |