24INR0378 · BESS · Jones County

Solara BESS 1

Solara BESS 1 is a 150 MW battery storage project in Jones County, Texas, connecting at 60387 Hendrick 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/30/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0378
Capacity
150 MW
Fuel
BESS (BA)
Interconnecting entity
CED Development Inc.
Projected COD
11/30/2027
Entered queue
07/05/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/26/2022
    Screening → FIS Requested
  • 07/05/2022
    Entered the queue with 150 MW, projected COD 11/30/2027

Other projects at this substation

Solara BESS 2BESS150 MWFIS Requested