24INR0109 · BESS · Victoria County
Oriana BESS
Withdrawn
Oriana BESS is a 60 MW battery storage project in Victoria County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0109
- Capacity
- 60 MW
- Fuel
- BESS
- Substation
- Not listed
- County
- Victoria County
- Interconnecting entity
- Not listed
- Projected COD
- n/a
- Entered queue
- 03/06/2026
- ERCOT zone
- n/a
- Size category
- n/a
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/06/2026Listed as inactive
Other projects at this substation
No other projects at this substation.