LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0098 · BESS · Jack County

Dovetail Storage

Dovetail Storage is a 509 MW battery storage project in Jack County, Texas, connecting at Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/12/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0098
Capacity
509 MW
Fuel
BESS (BA)
Interconnecting entity
Hecate Energy Dovetail Storage LLC
Projected COD
04/12/2028
Entered queue
09/28/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/31/2022
    Screening → FIS Requested
  • 09/28/2021
    Entered the queue with 509 MW, projected COD 04/12/2028

Other projects at this substation

Dovetail Solar 1Solar666 MWFIS Requested