24INR0094 · Solar · Jack County
Dovetail Solar 1
Dovetail Solar 1 is a 666 MW solar project in Jack County, Texas, connecting at Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/12/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0094
- Capacity
- 666 MW
- Fuel
- Solar (PV)
- County
- Jack County
- Interconnecting entity
- Hecate Energy Dovetail Solar 1 LLC
- Projected COD
- 04/12/2028
- Entered queue
- 09/21/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/06/2022Screening → FIS Requested
- 09/21/2021Entered the queue with 666 MW, projected COD 04/12/2028
Other projects at this substation