23INR0487 · Solar · Live Oak County

Brightside Solar Alt POI

COD date passed

Brightside Solar Alt POI is a 50 MW solar project in Live Oak County, Texas, connecting at 8156 Charter Substation 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/14/2026. Its projected COD of 08/14/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0487
Capacity
50 MW
Fuel
Solar (PV)
Interconnecting entity
Brightside Solar, LLC
Projected COD
08/14/2026
Entered queue
06/11/2020
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/11/2020
    Entered the queue with 50 MW, projected COD 08/14/2026
  • 06/11/2020
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.