Counties / Texas
Live Oak County power projects
Live Oak County, Texas has 5 active power projects totalling 323 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 221 MW (69%). The largest single project is Anagram Solar (131 MW solar). 2 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
5
0.3 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Live Oak County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Anagram Solar | Solar | 131 | 8156 Charter 138 kV | FIS Requested | 12/31/2027 |
| Bird Dog Energy Storage | BESS | 60 | 5669 Argenta 69kV | Sync Approved | 10/23/2026 |
| Brightside Solar Alt POI | Solar | 50 | 8156 Charter Substation 138kV | IA Signed | 08/14/2026 |
| Buck Ranch Solar SLF | Solar | 41 | 5690 WEST GEORGE WEST SUB 69kV | FIS Requested | 08/02/2028 |
| Buck Ranch Storage SLF | BESS | 41 | 5690 WEST GEORGE WEST SUB 69kV | FIS Requested | 08/09/2028 |
| Urca Solar | Solar | 204 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Live Oak County?
- ERCOT's October 2026 report lists 5 active projects in Live Oak County totalling 323 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.