23INR0228 · Solar · Clay County
Hiru Solar
Hiru Solar is a 604 MW solar project in Clay County, Texas, connecting at Tap 345kV 6111 Riley - 1730 West Krum ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0228
- Capacity
- 604 MW
- Fuel
- Solar (PV)
- County
- Clay County
- Interconnecting entity
- Hecate Energy Hazel LLC
- Projected COD
- 04/01/2029
- Entered queue
- 04/21/2021
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/30/2021Screening → FIS Requested
- 04/21/2021Entered the queue with 604 MW, projected COD 04/01/2029
Other projects at this substation
| Hiru Storage | BESS | 504 MW | FIS Requested |