ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0228 · Solar · Clay County

Hiru Solar

Hiru Solar is a 604 MW solar project in Clay County, Texas, connecting at Tap 345kV 6111 Riley - 1730 West Krum ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0228
Capacity
604 MW
Fuel
Solar (PV)
Interconnecting entity
Hecate Energy Hazel LLC
Projected COD
04/01/2029
Entered queue
04/21/2021
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/30/2021
    Screening → FIS Requested
  • 04/21/2021
    Entered the queue with 604 MW, projected COD 04/01/2029

Other projects at this substation

Hiru StorageBESS504 MWFIS Requested