23INR0200 · BESS · Atascosa County

Paradiso BESS

Paradiso BESS is a 102 MW battery storage project in Atascosa County, Texas, connecting at 8203 Pleasanton 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0200
Capacity
102 MW
Fuel
BESS (BA)
Interconnecting entity
VESI 13
Projected COD
03/15/2028
Entered queue
03/01/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/18/2025
    FIS Requested → IA Signed
  • 08/20/2021
    Screening → FIS Requested
  • 03/01/2021
    Entered the queue with 102 MW, projected COD 03/15/2028

Other projects at this substation

No other projects at this substation.