23INR0078 · Solar · Bandera County
Shaw Solar
Shaw Solar is a 125 MW solar project in Bandera County, Texas, connecting at Tap 138kV 7146 Verde Creek - 7438 Bandera. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/16/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0078
- Capacity
- 125 MW
- Fuel
- Solar (PV)
- County
- Bandera County
- Interconnecting entity
- Rio Lago Solar, LLC
- Projected COD
- 10/16/2026
- Entered queue
- 10/23/2020
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/31/2026Energization Approved → Sync Approved
- 06/04/2026IA Signed → Energization Approved
- 03/12/2025FIS Requested → FIS Approved
- 02/17/2023FIS Approved → IA Signed
- 05/11/2021Screening → FIS Requested
- 10/23/2020Entered the queue with 125 MW, projected COD 10/16/2026
Other projects at this substation
No other projects at this substation.