22INR0274 · Solar · Jones County

Crowded Star Solar II

Crowded Star Solar II is a 190 MW solar project in Jones County, Texas, connecting at tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/18/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0274
Capacity
190 MW
Fuel
Solar (PV)
Interconnecting entity
Jones City Solar II, LLC
Projected COD
09/18/2026
Entered queue
12/17/2019
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/08/2026
    Energization Approved → Sync Approved
  • 06/22/2026
    IA Signed → Energization Approved
  • 11/05/2024
    FIS Requested → FIS Approved
  • 03/24/2021
    Screening → FIS Requested
  • 12/17/2019
    Entered the queue with 190 MW, projected COD 09/18/2026
  • 12/17/2019
    FIS Approved → IA Signed