21INR0263 · Wind · Throckmorton County

Monarch Creek Wind

Monarch Creek Wind is a 283 MW wind project in Throckmorton County, Texas, connecting at 11419 Coody Crossing Switch 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0263
Capacity
283 MW
Fuel
Wind (WT)
Interconnecting entity
MONARCH CREEK WIND, LLC
Projected COD
09/17/2027
Entered queue
04/25/2019
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/05/2025
    FIS Requested → FIS Approved
  • 08/24/2020
    FIS Approved → IA Signed
  • 08/05/2019
    Screening → FIS Requested
  • 04/25/2019
    Entered the queue with 283 MW, projected COD 09/17/2027

Other projects at this substation