21INR0253 · Solar · Coke County

Ulysses Solar

COD delayed 1×

Ulysses Solar is a 151 MW solar project in Coke County, Texas, connecting at 60072 Odysseus Substation 345 kV. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 03/17/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0253
Capacity
151 MW
Fuel
Solar (PV)
Interconnecting entity
BNB Tennyson Solar LLC
Projected COD
03/17/2027
Entered queue
01/25/2019
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 03/02/2027 → 03/17/2027 (0 months)
  • 09/18/2026
    IA Signed → Energization Approved
  • 12/15/2025
    FIS Requested → FIS Approved
  • 10/03/2022
    FIS Approved → IA Signed
  • 05/10/2019
    Screening → FIS Requested
  • 01/25/2019
    Entered the queue with 151 MW, projected COD 03/02/2027

Other projects at this substation

No other projects at this substation.