ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
19INR0035 · Solar · Runnels County

Norton Solar

Norton Solar is a 128 MW solar project in Runnels County, Texas, connecting at 60451 Garnet 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/24/2025.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0035
Capacity
128 MW
Fuel
Solar (PV)
Interconnecting entity
TAI Norton Solar, LLC
Projected COD
11/24/2025
Entered queue
03/06/2017
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/06/2025
    Energization Approved → Sync Approved
  • 07/24/2025
    IA Signed → Energization Approved
  • 10/29/2024
    FIS Requested → FIS Approved
  • 06/20/2019
    FIS Approved → IA Signed
  • 11/08/2017
    Screening → FIS Requested
  • 03/06/2017
    Entered the queue with 128 MW, projected COD 11/24/2025

Other projects at this substation

No other projects at this substation.