Sutton County power projects

Sutton County, Texas has 2 active power projects totalling 307 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 307 MW (100%). The largest single project is Sonora High Noon BESS (204 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
2
0.3 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Sutton County

Withdrawn
09/16/2026
Axis Ridge Wind · Wind · Sutton County
Listed as cancelled by ERCOT.
−392 MW

All projects

ProjectFuelMWSubstationStageCOD
Sonora High Noon BESSBESS20460412 CARVER 138kVFIS Requested07/01/2028
Atticus Energy StorageBESS103Tap 69 KV 6570 Bond Road - 6513 SonoraFIS Requested01/26/2030
Axis Ridge WindWind39260210 Friess Ranch 138KVWithdrawn03/19/2030

For residents and landowners

What power projects are planned in Sutton County?
ERCOT's October 2026 report lists 2 active projects in Sutton County totalling 307 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.