ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Hays County power projects

Hays County, Texas has 5 active power projects totalling 147 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 75 MW (51%). The largest single project is PaleAle BESS (75 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
5
0.1 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Hays County

COD change
10/01/2026
Hays Energy Unit 3 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Hays Energy Unit 2 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Hays Energy Unit 1 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Hays Energy Unit 4 Repower · Gas · Hays County
Projected COD moved 07/01/2027 → 07/01/2028. Delay #1 for this project.
+12 mo

All projects

ProjectFuelMWSubstationStageCOD
PaleAle BESSBESS75Tap 138 kV Bus 7506 L_CEDAVA8_1Y - Bus 7507 L_FRIEND8_1YFIS Approved04/15/2027
Hays Energy Unit 3 RepowerGas187043 Hays 345kVFIS Requested07/01/2028
Hays Energy Unit 2 RepowerGas187043 Haysen 345kVFIS Requested07/01/2028
Hays Energy Unit 1 RepowerGas187043 Hays Energy 345kVFIS Requested07/01/2028
Hays Energy Unit 4 RepowerGas187043 Hays Energy 345kVFIS Requested07/01/2028

For residents and landowners

What power projects are planned in Hays County?
ERCOT's October 2026 report lists 5 active projects in Hays County totalling 147 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.