Gonzales County power projects
Gonzales County, Texas has 7 active power projects totalling 1,172 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 844 MW (72%). The largest single project is Columbine Wind (295 MW wind). 3 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
7
1.2 GW capacity
IA signed or later
3
43% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Gonzales County
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Columbine Wind | Wind | 295 | TAP 345KV BUS #5380 SHAULA- BUS #5133 ELM CREEK | FIS Requested | 09/01/2029 |
| Nockenut Springs Solar 3 | Solar | 201 | tap 345kV 5133 Elm Creek - 5915 STP ckt 1 | FIS Requested | 06/05/2029 |
| Nockenut Springs Solar 4 | Solar | 201 | The 345 kV Elm Creek - South Texas Project Line (Bus #5133 - #5915) | FIS Requested | 06/05/2029 |
| Nockenut Springs Solar 5 | Solar | 201 | Tap 345 kV 5133 Elm Creek - 5915 South Texas Project | FIS Requested | 06/05/2029 |
| Starling Solar | Solar | 145 | 138-kV Birdhouse (7255) | IA Signed | 01/28/2028 |
| Hoke Solar | Solar | 95 | tap 138kV 7595 Deer Creek - 7621 Nixon | IA Signed | 07/05/2027 |
| Hoke Storage | BESS | 33 | tap 138kV 7595 Deer Creek - 7621 Nixon | IA Signed | 07/05/2027 |
| Starling Storage | BESS | 64 | tap 138kV 7224 Luling - 7245 Gonzales | Withdrawn | 05/15/2027 |
For residents and landowners
- What power projects are planned in Gonzales County?
- ERCOT's October 2026 report lists 7 active projects in Gonzales County totalling 1,172 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.