Substation / point of interconnection ยท Ward County
#11098 Sand Lake Switch Station (SANDLAKE_5) 345kV
1 active project totalling 208 MW is queued to connect at #11098 Sand Lake Switch Station (SANDLAKE_5) 345kV in Ward County, Texas, according to ERCOT's October 2026 report.
Active capacity
208 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0255 | New Minglewood Energy Center | BESS | 208 | FIS Requested | 09/29/2029 | 0 |