LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Waller County

Tap 138kV 44750 FULSHR_S25_8 to 44860 TWINWD_S25_8

1 active project totalling 154 MW is queued to connect at Tap 138kV 44750 FULSHR_S25_8 to 44860 TWINWD_S25_8 in Waller County, Texas, according to ERCOT's October 2026 report.

Active capacity
154 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0426Maderagemela BESS1BESS154IA Signed02/01/20290