2 active projects totalling 202 MW are queued to connect at Ozark Trail Switch 345kV substation (Bus #23901) in Swisher County, Texas, according to ERCOT's October 2026 report.

Active capacity
202 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0282Hornet Solar II SLFSolar202IA Signed07/31/20280
25INR0283Hornet Storage II SLFBESS0IA Signed07/31/20280