new 345kV sub Kress connecting both 23912 Ogallala - 23914 Tule Canyon circuits
1 active project totalling 504 MW is queued to connect at new 345kV sub Kress connecting both 23912 Ogallala - 23914 Tule Canyon circuits in Swisher County, Texas, according to ERCOT's October 2026 report.
Active capacity
504 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 22INR0402 | Frye Storage | BESS | 504 | FIS Requested | 12/01/2028 | 0 |