Substation / point of interconnection ยท Sterling County
76030 Gasconades Creek 345kV
1 active project totalling 303 MW is queued to connect at 76030 Gasconades Creek 345kV in Sterling County, Texas, according to ERCOT's October 2026 report.
Active capacity
303 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0367 | Goat Mountain Wind-Repower | Wind | 303 | IA Signed | 03/01/2027 | 0 |