Substation / point of interconnection ยท Scurry County
59912 GALVANI 345
2 active projects totalling 200 MW are queued to connect at 59912 GALVANI 345 in Scurry County, Texas, according to ERCOT's October 2026 report.
Active capacity
200 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 27INR0623 | Helion Solar | Solar | 100 | FIS Requested | 10/22/2027 | 0 |
| 27INR0624 | Helion BESS | BESS | 100 | FIS Requested | 09/16/2027 | 0 |