ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Schleicher County

Tap 345kV line Big Hill (#76003) - Twin Buttes (#76009)

2 active projects totalling 604 MW are queued to connect at Tap 345kV line Big Hill (#76003) - Twin Buttes (#76009) in Schleicher County, Texas, according to ERCOT's October 2026 report.

Active capacity
604 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0290Cold Creek Solar 2Solar432IA Signed05/28/20280
26INR0291Cold Creek Storage 2BESS172IA Signed05/28/20280