LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Schleicher County

6500 Live Oak AEP 138kV

1 active project totalling 150 MW is queued to connect at 6500 Live Oak AEP 138kV in Schleicher County, Texas, according to ERCOT's October 2026 report.

Active capacity
150 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0364Cashel BESSBESS150FIS Requested03/15/20280