Substation / point of interconnection · San Patricio County
Tap 345kV 8249 Angstrom – 8659 Naismith
2 active projects totalling 565 MW are queued to connect at Tap 345kV 8249 Angstrom – 8659 Naismith in San Patricio County, Texas, according to ERCOT's October 2026 report.
Active capacity
565 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0081 | SanPat Solar I | Solar | 309 | IA Signed | 07/08/2027 | 0 |
| 25INR0052 | SanPat Solar II | Solar | 256 | IA Signed | 07/22/2027 | 0 |