2 active projects totalling 603 MW are queued to connect at Tap 345 kV 8249 Angstrom - 8624 Grissom in San Patricio County, Texas, according to ERCOT's October 2026 report.

Active capacity
603 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0492Gulf Gateway Solar OneSolar301FIS Requested12/01/20290
27INR0556Gulf Gateway Storage OneBESS301FIS Requested12/01/20290