Substation / point of interconnection ยท San Patricio County
KATOEN (Bus#8579)
2 active projects totalling 558 MW are queued to connect at KATOEN (Bus#8579) in San Patricio County, Texas, according to ERCOT's October 2026 report.
Active capacity
558 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0179 | Sunburst Solar | Solar | 302 | FIS Requested | 03/16/2029 | 0 |
| 28INR0181 | Sunburst BESS | BESS | 256 | FIS Requested | 03/16/2029 | 0 |