Substation / point of interconnection ยท Robertson County
Tap connection to a new switching station on the Elliott (Bus #53) - Franklin (Bus #57) 69 kV Transmission Line
1 active project totalling 50 MW is queued to connect at Tap connection to a new switching station on the Elliott (Bus #53) - Franklin (Bus #57) 69 kV Transmission Line in Robertson County, Texas, according to ERCOT's October 2026 report.
Active capacity
50 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0498 | Stegall Storage | BESS | 50 | FIS Approved | 05/30/2027 | 0 |