Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2

8 active projects totalling 817 MW are queued to connect at Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2 in Robertson County, Texas, according to ERCOT's October 2026 report.

Active capacity
817 MW
queued at this substation
Active projects
8
8 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0418Pioneer Path Energy Storage 1BESS102FIS Requested12/01/20270
27INR0423Pioneer Path Energy Storage 2BESS102FIS Requested12/01/20270
27INR0424Pioneer Path Energy Storage 3BESS102FIS Requested12/01/20270
27INR0425Pioneer Path Energy Storage 4BESS102FIS Requested12/01/20270
27INR0426Prairie Horizon Energy Storage 1BESS102FIS Requested12/01/20270
27INR0427Prairie Horizon Energy Storage 2BESS102FIS Requested12/01/20270
27INR0428Prairie Horizon Energy Storage 3BESS102FIS Requested12/01/20270
27INR0429Prairie Horizon Energy Storage 4BESS102FIS Requested12/01/20270