Substation / point of interconnection · Refugio County
tap the 345 kV Angstrom (#8249) – Static (#8676) line; AEP
1 active project totalling 511 MW is queued to connect at tap the 345 kV Angstrom (#8249) – Static (#8676) line; AEP in Refugio County, Texas, according to ERCOT's October 2026 report.
Active capacity
511 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0156 | Ross Storage | BESS | 511 | IA Signed | 07/31/2027 | 0 |